Apply for an HDB Flat Eligibility (HFE) letter, then for a BTO; a ballot decides who picks a unit. HDB gives each project's waiting time at launch: in its 4 Nov 2026 exercise, under three years at Sembawang Anchor and under four at the other six. Standard flats carry a 5-year MOP, Plus and Prime a 10-year MOP.
Steps
- Apply for an HFE letter to check eligibility, the loan and grants.
- Browse the next sales exercise and choose a project and flat type.
- Submit your application; wait for the ballot result.
- Select a unit when invited, sign the agreement and pay the downpayment.
- Collect keys on completion; the MOP starts from key collection.
Standard, Plus and Prime
Plus and Prime projects, typically in more central or sought-after locations, carry longer MOPs and resale conditions such as a subsidy recovery on sale. Standard flats have the usual 5-year MOP and no subsidy recovery. Check HDB for the current terms of each project.
Frequently asked questions
How long does a BTO take?
HDB publishes each project's estimated waiting time at launch. For its 4 Nov 2026 launch, Sembawang Anchor is under three years and the other six projects under four. HDB's 1 Nov 2026 release gives 2 years 10 months for Sembawang Anchor and 3 years 2 months for Bayshore Oasis and Plantation Dew.